Skip to content

Planning the line ​

The Scheduler shows your production line as a ribbon of time: every run of bags, in order, with the time between runs and the time nobody has sold yet. You plan by dragging runs, and Otto keeps the rest of the line in order.

Open it from Inventory Manager → Scheduler. The Scheduler is turned on per workspace. If you don't see it, contact Otto support.

Times are on the plant's clock ​

Every date and time on the page is in your plant's time zone, wherever you are. If your computer is set to another time zone, the top of the page says so, for example "Times in Chicago time." Edit as a list and the downtime form use the same clock, so a run typed in for 6:00 AM starts at 6:00 AM at the plant.

The top of the page also says how your line runs, for example "Runs 24/7. 20 minutes per changeover."

The Week view ​

Week shows five weeks, one ribbon each, starting with this week. Use ‹ and › to move a week at a time, and This week to come back.

Each ribbon is one week of the line, left to right:

  • Runs are coloured blocks, as wide as the hours they take. Each speed group has a colour, and each product in a group its own shade of it. A wide enough block shows its product and bags, for example "3# Gala 686k".
  • Changeovers are the thin dark notches just before a run. The line stops for a changeover whenever it switches to a different product. The same product back to back needs no changeover.
  • Downtime is hatched dark. Point at it to see the reason and times.
  • Not sold yet is the striped background: time the line has nothing planned for.
  • Time gone is the flat grey at the start of this week's ribbon.
  • Now is a thin blue line.
  • Late runs have a red bar across their top (see below).

The key under the ribbons lists every speed group with its speed, for example "3#, 380 a minute". Runs for products in no group show as "No speed group".

Bags open ​

Each week ends with its Bags open: how many more bags the line could make in that week's unsold time. The colour tells you how much of the week is still free:

  • Red: half or more of the week's remaining time is unsold.
  • Plain text colour: some of it is unsold.
  • Green: under 15% is unsold. The week is nearly full.

Point at the number to see the share, for example "62% of the week's time left is open". A week that is over shows "–".

The headline ​

Above the ribbons, a large number totals the bags open across the five weeks, for example "9.2M bags the line can still make in the next 5 weeks". Once you move off this week, it reads "bags open in these 5 weeks".

Next to it, Lightest week names the week with the most bags open, for example "Lightest week: Tue Nov 17, 3.7M open." That is the week to sell into first.

What "bags open" counts ​

  • Only time from now on. Hours already gone this week never count as open.
  • The line's calendar time, less the runs, changeovers and downtime in it. Where two of those overlap, the time counts once.
  • Bags at the line's default speed, for example 380 a minute, whatever product you might put there. A slower product would make fewer bags in the same time.

The Day view ​

Day shows one day, midnight to midnight, marked every two hours. Use ‹ and › to move a day at a time, and Today to come back.

Three numbers sit above the day:

  • bags planned today: the bags of every run on the line that day. A run that crosses midnight counts only the share of its hours that fall in the day, so no bag is counted on two days.
  • bags of open time left (about N hours): the bags the line could still make in the day's unsold time, and how many hours that is. Like the weeks, it counts only time from now on.
  • changeovers, N minutes changing over: how many changeovers fall in the day, and how many minutes the line stops for them.

Run like products together ​

Once your workspace has a product family or a product attribute, the Day view shows a Group by box. Families and attributes are set in Settings → Products (see Families and attributes); rate groups in Run rates, in the Scheduler setup at the bottom of this page, and once the box shows they are one of its choices. Pick Family, Rate group or an attribute, and the day's runs are listed under the timeline by group, with each group's bags. A group's bags are the whole of each run that starts that day, so they can differ from bags planned today, which counts only the hours inside the day. A run marked no changeover follows the same product, so the line won't stop before it.

Sort today's runs shows the day before and after sorting it by that group, and how many changeovers that saves, or adds. Runs already under way stay where they are. If sorting would also move runs on another day, Otto lists them and asks you again before moving anything; if the schedule changes meanwhile (a run added to the day, or more runs that would move), Otto shows you the new order instead of moving them. Nothing moves until you press Move runs. No setting to turn on: the box shows once you add a family or an attribute, and until then the Day view is unchanged.

The 7 days view ​

7 days shows a week with one row per day, midnight to midnight, marked every two hours. Under each day, every run is listed with its times, its whole product name and its bags. A run that crosses midnight appears on both days with that day's share of the bags. Use the arrows to move a week.

You can move a run here the same way as in the Day view, including onto another day.

In the 7 days view, click Print or save as PDF, then choose your printer or Save as PDF in the print window. You get the week on screen, with a strip and a list of runs for each day, and the time it was printed. A printout doesn't update, so print a new one after the schedule changes.

Once a product has a customer, the 7 days view shows a Customer menu next to Print or save as PDF. Choose a customer and the lists under each day show only their runs. The other runs stay on the rows, faint, so you can still see the line is busy.

Print with a customer chosen and the sheet has only that customer's runs and bags, with their name at the top. It leaves out downtime and other customers, so you can send it to them.

To set a product's customer, open the product in Inventory, click Edit item and choose Customer. A run from a customer order shows that order's customer instead.

Mark a product high urgency ​

In Inventory, open the product, click Edit item and tick High urgency. Its runs get an orange bar along the bottom and say High urgency in the run panel, the list under each day and the printed sheet. It doesn't move anything on the schedule.

Add a run ​

Use Add run, next to Day, 7 days, Week and Month, for a run that isn't on a customer order yet.

  1. Pick the Product. The products already on this line come first. If it isn't there, choose New product… and type its name. It's added to your products in Inventory, where you can set its customer and size group later.
  2. Enter the Bags, for example 400,000.
  3. Choose when:
    • First open time puts it in the first gap from now that it fits, so nothing else moves.
    • Pick a time starts it at the date and time you choose. If that time is inside another run, it starts right after that run. Runs after it move later, with the changeover.
  4. Add a Due date if it has one. The run shows as late if it finishes after that day.
  5. Click Add run. The line says what was added and when it starts, and how many runs moved.

The run's hours come from its size group's rate, or the line's rate if it has no group. Its customer comes from the product.

Delete a run ​

Click a run and choose Delete run in the panel, or click Delete on its row under Edit as a list. The runs after it on that line move up to close the gap: "Deleted 3# Gala. 4 runs moved up to close the gap." Each moves up only as far as its materials, downtime and changeovers allow, and open time you already had between runs stays. It can't be undone.

You can't delete a run that has started on the line or finished. If the run was the last one for a customer order line, that line comes off Make on our line, and the order itself doesn't change.

The Month view ​

Month shows every week that touches a calendar month, four to six ribbons. Days outside the month are shaded. Use ‹ and › to move a month at a time, and This month to come back. The headline totals the bags open in those weeks.

See a run ​

Click a run to open it in the Selected run panel. It shows:

  • the product, and a red Late by N hours badge if it is late;
  • Bags, Speed (for example "380 a minute") and Takes (its hours);
  • Runs: when it starts and finishes;
  • Order: the customer order it is for, for example "CO-4512, Orchard Foods". Click it to open the order. A run that isn't from a customer order says "Not from a customer order".

Change the bags ​

Type the new number in Bags to make and choose Save bags. Otto re-times the run from its speed, and if it now takes longer, the runs after it move later to make room. The status line says, for example, "Saved: 844,000 bags. 2 later runs pushed back."

A run always takes at least 15 minutes on the schedule, even when its bags would take less. Anything longer takes exactly the time its bags need: a 50,000-bag run at 380 a minute takes about 2.2 hours.

Move a run ​

Drag a run to where you want it: later in the same week, into another week, or into open time. It snaps to the nearest 15 minutes.

  • The runs after it move along. If you drop a run on top of another, it lands right after that run, plus a changeover if the products differ, and every run behind it moves later to make room. Nothing ends up overlapping.
  • Move a run later and the gap it leaves closes. The runs it jumped over move up into its old slot. Drop it onto or just after other runs and it lands right behind them, so the line stays packed. Drop it into open time further out and it keeps the time you dropped it at. Move it to another line and the runs after it on the old line move up. Each run moves up only as far as its materials, downtime and changeovers allow, and open time you already had between runs stays.
  • Nudging a run a little later closes nothing. If it doesn't pass another run, the break you gave it stays.
  • Moving a run earlier doesn't pull others. The runs between its new and old place move later to make room, which fills its old slot. If you move a run and then move it back, the runs it pushed stay where they went.
  • To cancel a drag, press Esc before you let go, or let go where the run started. Nothing is saved.
  • It can't start in the past. Drop a run before now and it starts now: "It can't start in the past, so it starts now."
  • It can't start before its materials arrive: the film from its supplier orders (see Make on our line below) and any other materials expected for that product. Otto says "It can't start before its materials arrive, so it starts then."

After a move, the status line says "Moved." and how many later runs were pushed back. If the move can't be saved, the run goes back where it was and the status line says why.

In the Day view you can also drag a run's right edge to change its length, and so its bags. Otto rounds the bags to the nearest 1,000.

With the keyboard ​

Tab to a run. The left and right arrow keys move it an hour at a time, Enter saves and Esc cancels. In the Day view, hold Shift with the arrow keys to change its length. Moving to something else without pressing Enter drops the move.

Runs that can't move ​

  • A finished run stays where it ran. Its panel says "Finished."
  • A run whose actual start has been recorded says "Started on the line, so it stays where it is."

A run that is under way only by the clock, because its planned start has passed, can still move. Its panel says "Under way by the clock. Moving it starts it from now." Until you move it, the line treats it as running, and other runs move around it.

Late runs ​

A run is late when it finishes after the end of the due date of the customer order line it is for: the line's own need-by date, or else the order's requested delivery date. The due date ends at midnight on the plant's clock, so a run due Nov 20 that finishes at 10:00 AM on Nov 20, plant time, is on time. A late run's block has a red bar across the top, and its panel says, for example, "Late by 3 hours."

Supplier dates work the same way: film promised for Nov 12 counts from midnight at the start of Nov 12, plant time.

Otto never refuses a move because it makes a run late. You decide what to do: move a run ahead of it, change its bags, or talk to the customer.

Run rates and changeovers ​

The Run rates card is in Scheduler setup, at the bottom of the Scheduler page. It lists your speed groups, such as 2#, 3#, 5# and 10#, with how many bags a minute the line makes for each, and how many products are in each.

A product's speed comes from, in order:

  1. its own routing rate on that machine, if it has one;
  2. its speed group;
  3. the machine's default speed.

Everyone with the Scheduler can see the card. Only owners and admins can change it; everyone else sees "Only an owner or admin can change run rates."

Owners and admins can:

  • choose Edit on a group to change its name, Units a minute or colour, then Save;
  • add a group with New group, Units a minute and Colour, then Add group;
  • choose Products on a group to remove a product, or search under Add products to add one. A product already in another group says, for example, "moves it from 5#", because a product is in one group at a time;
  • choose Delete to remove a group. Its products use the machine's default speed instead, unless they have their own routing rate.

What changing a rate does ​

Changing a group's speed, moving a product between groups or deleting a group re-times every run of those products that hasn't started yet: "Saved. Runs that haven't started were re-timed." A run already under way keeps its length. If a run now takes longer, the runs after it move later. If it now takes less time, it leaves a gap; nothing moves earlier.

Changeover minutes ​

Under the groups, each machine has its changeover: the minutes the line stops to switch from one product to a different one. Owners and admins type the Minutes (a whole number from 0 to 1440) and choose Save.

If the new changeover means runs no longer fit, Otto moves the runs that haven't started later: "Saved. Runs that haven't started were moved later to fit." Otherwise it says "Saved. No runs needed to move."

Make on our line ​

A customer order only goes on the line when you say you'll make it yourselves. Anything you buy in finished never touches the schedule.

On a customer order, each line with a product has a Make on our line box. It shows only when the Scheduler is on, and not on cancelled or received orders. Anyone who can edit orders can tick it.

Ticking the box ​

Otto puts the line on the schedule as one run, in the first open time on the line long enough for it, from now on and no earlier than its film and other materials arrive. It doesn't move any other run to make room. Under the box Otto says when it starts, for example "On the schedule from Nov 10, 2026", and "Late by N hours" if it would finish after the due date. Drag it in the Scheduler if you want it somewhere else.

Ticking a line that is already on the schedule leaves its run alone.

Unticking the box ​

Otto takes the line's run off the schedule. That leaves a gap; it doesn't pull later runs earlier.

If the run has already started, it stays: "Already running; it stays on the schedule."

Cancelling or deleting the order ​

Cancelling a customer order, deleting it, or deleting one of its lines while it is a draft takes those lines' runs off the schedule the same way: runs that haven't started go, and a run that has started stays.

When the film arrives ​

A run can't start before the film for it arrives. Otto looks at the supplier orders for that customer line: supplier order lines linked to it in For customer line, or made from the customer order with Order from supplier. A supplier order counts once it is approved, and stops counting when it is received or cancelled, or when every bag of film on it has arrived.

For each, Otto uses the date the supplier promised, or, until they promise one, the date you asked for. The run can't start before the latest of them.

The film isn't the only thing a run waits for: other materials Otto expects for the product hold it back the same way, until the date they're due. They show as Materials land in Edit as a list.

Otto checks those dates again whenever a supplier order is approved, acknowledged, marked shipped, received, revised or cancelled, and when you accept a date change from the supplier's email. If the film is now due later, the run moves to when the film arrives. Runs that could go before it keep their times; only runs that were already after that date move along to make room. If the film is due sooner, the run stays where it is. Runs that have started never move.

Downtime ​

Use Machine downtime, next to Edit as a list, to block out time the line can't run:

  1. Pick the Machine.
  2. Pick the Type: Planned (maintenance) or Unplanned (breakdown).
  3. Pick the First day and Last day. Downtime covers whole days, from midnight on the first day to midnight after the last.
  4. Add a Reason if you like. It shows when you point at the downtime on the ribbon.
  5. Choose Add downtime.

Runs that haven't started and fall in the downtime move to just after it, and the runs behind them move along: "Downtime added. 3 runs moved out of the way." A run already under way stays where it is.

Downtime can't yet be edited or removed from the page. Contact Otto support if you need one changed or taken off.

Edit as a list ​

Edit as a list, under the views, shows every run on every machine as a table. Type a new machine, start or hours instead of dragging; the same rules apply. After each change the line above the table says what happened, for example "Saved. 2 later runs pushed back.", or why it couldn't save.

Choose Mark finished when a run is done: Otto records its actual start and finish, and drafts the order-complete update for the customer for you to review. This can't be undone, and the run can't move after that. If you mark a run finished before its planned start, Otto counts it as having run just before now, so its planned slot opens up for other runs.

Questions this guide doesn’t answer — contact Otto support. · Privacy policy